PRF PRINCE2 Foundation exam introduces the PRINCE2 method and aims to confirm that you know and understand the PRINCE2 method well enough to be able to work effectively with, or as a member of, a project management team working within an environment supporting PRINCE2. The PRINCE2 Foundation certification is intended for project managers and aspiring project managers. Killtest provides the latest PRF PRINCE2 Foundation study guides, which are helpful for you to study this PRF exam and earn the related certification.
PRF PRINCE2 Foundation Exam
Read PRF PRINCE2 Foundation exam information in the following table.
PRINCE2 Foundation PRF Exam Syllabus
List PRINCE2 Foundation PRF exam syllabus below.
Learning outcome 1 - Understand key concepts relating to projects and PRINCE2
Learning outcome 2 - Understand how the PRINCE2 principles underpin the PRINCE2 method
Learning outcome 3 - Understand the PRINCE2 themes and how they are applied throughout the project
Learning outcome 4 - Understand the PRINCE2 processes and how they are carried out throughout the project
All of Killtest PRINCE2 Foundation PRF exam study guides can help you study the above exam syllabus well. Share some PRF PRINCE2 Foundation exam demo questions and answers below.
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Directing a Project
B. Starting up a Project
C. Controlling a Stage
D. Managing a Stage Boundary
Answer: C
What process provides the information required to decide whether to authorize the delivery of a project?
A. Directing a Project
B. Starting up a Project
C. Managing Product Delivery
D. Initiating a Project
Answer: D
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
A.Work Package
B.Project Plan
C.End Stage Report
D.Team Plan
Answer: B
Which does a Project Manager produce to define and control the work to be done?
A. Work Package
B. Configuration Item Record
C. Stage scope tolerance
D. Team Plan
Answer: A
Which is a purpose of a Lessons Report?
A. Improve the project management method for future projects
B. Provide a summary of the benefits realized during the project
C. Compare the actual performance of the final stage against its plan
D. Detail open issues and risks that need to be managed after the project has closed
Answer: A